A fuse cutout is the cheapest protection device on a medium voltage overhead feeder and one of the easiest to misapply. On its own, a drop-out cutout is a simple, reliable transformer and branch protector. Put an upstream recloser in front of it and the two devices start competing: whichever operates first decides whether a transient fault causes a momentary blink or a truck roll to replace a fuse link. Getting that interaction right is what protection engineers mean by coordination. This guide explains the curves, the two competing schemes and the verification steps for an 11kV feeder.

Role of the Drop-Out Fuse Cutout on an MV Feeder
A drop-out fuse cutout consists of an insulating support, a hinged fuse tube and a replaceable fuse link. When the element melts under fault current, the tube’s liner generates gas that expels the arc, the tube drops open, and the line crew gets a clearly visible isolation point. It is widely used on distribution transformer primaries, capacitor banks and lateral taps because it is inexpensive, needs no auxiliary supply and provides both protection and a visible break.
Two limitations shape the coordination problem. The cutout is a single-phase, one-shot device: once the link operates, someone has to replace it. And the expulsion mechanism needs fault current to generate the gas that clears the arc, so its performance at very low overcurrents is limited. Neither issue matters when the cutout is the only protection on a lateral; both matter a great deal when an upstream recloser versus circuit breaker scheme can trip and re-energise the same fault several times.
Fuse Element Characteristics and the Time-Current Curve
Every fuse link has two published time-current curves. The minimum melting curve shows how long the element takes to melt at a given current. The total clearing curve adds the arcing time and shows when the circuit is actually interrupted. On a log-log plot, both slope downward as current increases, and the gap between them is the arcing interval. Coordination uses both, for different purposes.
The curves are published for a defined ambient temperature and a cold, undamaged element. Repeated overloads close to the melting point can pre-damage a link without operating it, shifting its effective melting curve downward — a real-world reason a fuse “blows” at a current that the catalogue says it should withstand. Many coordination methods therefore apply a derating or coordination factor to the minimum melting curve rather than using it at face value. Review the electric fuse range alongside the manufacturer’s curve sheet before selecting a link rating.
Recloser Operating Sequences and Dead Times
A recloser clears a fault, waits through a dead time, closes again, and repeats a defined number of times before locking out. Typical sequences combine one or two fast operations using an instantaneous curve with one or two delayed operations using a time-overcurrent curve. The fast shots are intended to clear transient faults — a branch brushing a conductor, a lightning flashover — before any downstream fuse has time to melt. The delayed shots give downstream protection the chance to clear a permanent fault first, so that the whole feeder does not stay out.
Sequence details matter: dead time, the number of fast and delayed shots, the reset time after a successful reclose, and the cumulative heating of a fuse link across successive shots. A link might survive one fast shot with a small amount of pre-damage and then melt on the second, even though each individual shot looked safe on paper. Coordination factors exist precisely to account for that cumulative effect.
Fuse-Saving vs Fuse-Blowing Schemes
In a fuse-saving scheme, the recloser’s fast curve is set faster than the fuse’s minimum melting curve. A transient fault is cleared by the recloser, the fuse link survives, and reclosing restores supply without a site visit. The recloser’s delayed curve is set slower than the fuse’s total clearing curve, so a permanent fault is cleared by the fuse and only the affected lateral is lost. This is the standard approach where a feeder serves many fused laterals and crew travel is expensive.
In a fuse-blowing scheme, the fuse is allowed to operate before the recloser on all faults. The advantage is simplicity and fewer momentary interruptions on the main feeder; the cost is a fuse replacement for every transient fault. Utilities choose between the two based on the mix of transient versus permanent faults, the value placed on momentary interruptions, and the availability of field crews. Neither is universally correct — but the settings must be consistent with the chosen policy. The RW12 high voltage fuse is a typical distribution cutout where the link curve and the upstream setting need to be checked together.
Coordination Rules and Speed Ratios
Three comparisons define the study. The recloser fast curve must lie below and to the left of the fuse minimum melting curve over the full range of available fault currents at the cutout. The recloser delayed curve must lie above and to the right of the fuse total clearing curve. And the fuse must remain intact through transformer inrush and cold-load pickup while still clearing the minimum fault current at the far end of the lateral.
Engineers usually work with published coordination factors or “speed ratios” that give a safety margin between curves, rather than requiring the curves merely not to cross. Check the maximum and minimum fault current at the cutout, not just one value — at low fault current the curves may diverge in the wrong direction, and that is where coordination quietly fails. Confirm the recloser curve at the actual tap and settings used on site, and check the fuse curve for the exact link type, since a “K” link and a “T” link of the same nominal rating behave differently. The medium voltage switchgear protection schedule should record which combination was verified.
Worked Coordination Example for an 11kV Feeder
Consider an 11kV feeder with a recloser at the substation and a 1000kVA transformer on a fused lateral. Full-load current at 11kV is about 52.5A, so a link in the 65A to 100A range might be shortlisted depending on the utility’s practice, inrush margin and the transformer’s permitted overload. That choice is only the starting point.
Next, calculate the maximum three-phase fault current at the cutout and the minimum phase-to-earth fault current at the end of the protected section. Plot the recloser fast and delayed curves against the link’s minimum melting and total clearing curves across that full range. Verify the fast shot clears before melting at maximum fault current, that the delayed curve stays above total clearing at both ends of the range, and that the minimum fault current still melts the link within an acceptable time. Then check inrush: transformer energisation can draw many times rated current for a fraction of a second, and a link chosen too close to full load will nuisance-operate on reclosing into a cold transformer. The 11kV, 22kV and 33kV guide sets out the voltage-class context for these calculations.
Transformer Protection and Inrush Considerations
A distribution transformer primary fuse has to do three jobs that pull in different directions: tolerate magnetising inrush without melting, tolerate short-term overload without pre-damage, and clear a transformer internal fault quickly enough to limit damage. Inrush is a short, high-current pulse with a significant DC component; overload is a long, moderate current; an internal fault is a sustained high current. Reading the time-current curve at all three points is more useful than applying a single multiplier to full-load current.
Also plan for single-phasing. If one fuse link operates on a three-phase transformer bank, the remaining phases can continue to supply an unbalanced load and damage motors downstream. Striker-linked cutouts or three-phase gang operation can be used where the consequence is unacceptable. Note that a drop-out cutout is not normally a load-break device: opening it under load requires a separate load-break tool or switch, and that limitation belongs in the switching procedure.
Coordination Parameter Table
| Parameter | Source | Why it matters |
|---|---|---|
| Fuse minimum melting curve | Link manufacturer curve sheet | Upper bound for recloser fast operation |
| Fuse total clearing curve | Link manufacturer curve sheet | Lower bound for recloser delayed operation |
| Recloser fast / delayed curves | Controller settings and relay curves | Defines fuse-saving or fuse-blowing behaviour |
| Maximum and minimum fault current | Network impedance study | Coordination must hold across the whole range |
| Transformer inrush and cold load | Transformer data and load profile | Prevents nuisance operation on energisation |
| Reclose sequence and dead times | Protection setting file | Cumulative pre-damage of the link |
| Coordination factor | Utility practice or manufacturer guidance | Margin for pre-damage and curve tolerances |
Field Verification Checklist
| Check | Method | Acceptance basis |
|---|---|---|
| Installed link type and rating | Visual and asset register comparison | Matches the coordination study |
| Recloser settings | Read the setting file from the controller | Matches approved fast/delayed curves and sequence |
| Cutout condition | Inspect tube, contacts, hinge and drop action | Free movement, no tracking or corrosion |
| Upstream fault level | Recheck against current network configuration | Within the range used in the study |
| Post-fault link inspection | Replace rather than reuse after operation | No pre-damaged links left in service |
| Switching procedure | Confirm load-break method and visible break | Site safety rules and equipment capability |
Conclusion
Coordination is a curve-matching exercise with operational consequences. Define the policy first — fuse-saving or fuse-blowing — then plot the recloser’s fast and delayed curves against the link’s minimum melting and total clearing curves over the full fault-current range, and check inrush, cold load and cumulative pre-damage. Record the exact link type and controller settings in the protection schedule, and re-run the study whenever the network fault level or transformer capacity changes. A well-coordinated cutout turns most transient faults into a brief blink instead of a replacement call.
Frequently Asked Questions
What is the difference between fuse-saving and fuse-blowing?
Fuse-saving sets the recloser’s fast curve faster than the fuse’s minimum melting curve, so transient faults clear before the link is damaged. Fuse-blowing lets the fuse operate first on all faults, avoiding momentary main-feeder interruptions at the cost of a link replacement for every transient event.
Why does a fuse cutout have two time-current curves?
The minimum melting curve shows when the element melts; the total clearing curve adds arcing time and shows when the circuit is actually interrupted. Recloser fast curves are compared with the former, delayed curves with the latter.
Can a drop-out cutout interrupt load current?
Not normally. A standard cutout is a fault-protection device, not a load-break switch. Opening it under load requires an approved load-break tool or a separate switch, and that requirement should be written into the switching procedure.
How do I choose a fuse link rating for a distribution transformer?
Start from the transformer’s full-load primary current, then check magnetising inrush, permitted short-term overload, minimum fault current at the end of the protected section, and the upstream recloser curves. A single multiplier on full-load current is not a complete method.
What happens if only one fuse operates on a three-phase bank?
The remaining phases can keep supplying an unbalanced load, risking damage to downstream motors. Where that consequence is unacceptable, use striker-linked cutouts or gang-operated three-phase arrangements.